Progress of construction works at Mantera Seaview residence

Overall readiness of the residences is 75,5%

Walls and partition walls are 88% complete. 60% of the facade has been insulated. Roof installation is nearing completion.
Installations and shell and core fit out are 84% ready. Final finishing is being carried out.
Walls are being put up, roofs and installations are being mounted, shell and core fit out is being carried out in urban villas.
Completion of the five-star hotel: 65%.
Glazing is 81% complete.
Progress in roof installation: 73%.
The conference hall is being built. Completion of the building: 63%.